Roadworks around Shepherd's Bush


Where to expect traffic delays in the days ahead

A315/B408 Glenthorne Road, London, Hammersmith And Fulham
19 January — 30 January
Delays likely Lane closure
Works location: A315/B408
Works description: Excavate And Install Cw2 Chamber, Slew Level 3 Duct From Existing Cw2 Chamber In Cw And Fw
Responsibility for works: Global Crossing (UK) Telecommunications
Current status: Planned work about to start
A315 Hammersmith Road, London, Hammersmith And Fulham
19 January — 25 January
Delays likely Traffic control (multi-way signals)
Works location: A315
Works description: Installation Of Telecom Ducts And Chambers In C/W - Following Site Meeting New Dates Agreed
Responsibility for works: euNetworks
Current status: Planned work about to start
A40 Westway, London, Hammersmith And Fulham
20 January — 21 January
Delays likely Road closure
Works location: A40
Works description: Expansion Joints Monitoring Inspection Full Closure And Diversion 00:00 - 05:00
Responsibility for works: Transport For London
Current status: Advanced planning
A40 Westway, London, Hammersmith And Fulham
20 January — 22 January
Delays likely Road closure
Works location: A40
Works description: Wp Cycle Super Highway Investigation Works Full Closure & Diversions Eb Night Works 0000 To 0500
Responsibility for works: Transport For London
Current status: Advanced planning
B317 North End Road, London, Hammersmith And Fulham
19 January — 25 January
Delays likely Traffic control (multi-way signals)
Works location: B317
Works description: Sec 81 Frame And Cover Repair - Works To Be Carried Out Within Jsm'S Existing Tm
Responsibility for works: Abovenet Communications UK Ltd
Current status: Planned work about to start
B317 North End Road, London, Hammersmith And Fulham
19 January — 25 January
Delays likely Traffic control (multi-way signals)
Works location: B317
Works description: Installation Of Telecom Ducts And Chambers In C/W - Following Site Meeting New Dates Agreed.
Responsibility for works: euNetworks
Current status: Planned work about to start
B450 Ladbroke Grove, London, Kensington And Chelsea
19 January — 16 March
Delays likely Lane closure
Works location: B450
Works description: Junction Modernisation Works - In Conjunction With Tfl'S Signal Mods Programme, Rbkc Will Be Upgrading The Streetscape Around The Junctions. Works Will Include Upgraded Traffic Islands, Repaved Footways And Improved Crossing Facilities.
Responsibility for works: Kensington and Chelsea Royal Borough Council
Current status: Planned work about to start
West Cross Route (A3220), London, Hammersmith And Fulham
19 January — 21 January
Delays likely Lane closure
Works location: -
Works description: -
Responsibility for works: Transport For London
Current status: Planned work about to start
A219 Shepherd'S Bush Road, London, Hammersmith And Fulham
20 January — 20 January
Delays possible Some carriageway incursion
Works location: A219
Works description: District Metering Miscellaneous Repair - Surface B--Works Intended To Include First Time Permanent Reinstatement Within Same Phase
Responsibility for works: Thames Water
Current status: Planned work about to start
A219 Wood Lane, London, Hammersmith And Fulham
19 January — 01 February
Delays possible Some carriageway incursion
Works location: A219
Works description: Installation Of Teleocms, Chambers And Ducts In F/Way Only No Impact On C/Way
Responsibility for works: City of London Telecomms
Current status: Planned work about to start
A315 Beadon Road, London, Hammersmith And Fulham
19 January — 21 January
Delays possible Some carriageway incursion
Works location: A315
Works description: Connections Highway Services:Works For Road Purposes: (Notice For Information Only):Interim To Perm
Responsibility for works: Hammersmith and Fulham London Borough Council
Current status: Planned work about to start
A315 Hammersmith Road, London, Hammersmith And Fulham
20 January — 22 January
Delays possible Some carriageway incursion
Works location: A315
Works description: Section 81 - To Reset 0.6x0.6 Gaas Box In Sma Cwy
Responsibility for works: National Grid Gas Plc
Current status: Planned work about to start
A4020 Uxbridge Road, London, Hammersmith And Fulham
20 January — 21 January
Delays possible Some carriageway incursion
Works location: A4020
Works description: Customer Connection New Residential Supply. Clear Blocked Duct & Repair Blockages If Found Footway Works Only
Responsibility for works: Virgin Media
Current status: Planned work about to start
A4020 Uxbridge Road, London, Hammersmith And Fulham
20 January — 21 January
Delays possible Some carriageway incursion
Works location: A4020
Works description: Clear Blocked Duct & Repair Blockages If Found Footway Works Only
Responsibility for works: Virgin Media
Current status: Planned work about to start
A4020 Uxbridge Road, London, Hammersmith And Fulham
20 January — 22 January
Delays possible Some carriageway incursion
Works location: A4020
Works description: Section 81 - To Renew Valve Box In F/W
Responsibility for works: National Grid Gas Plc
Current status: Planned work about to start
A402 Goldhawk Road, London, Hammersmith And Fulham
19 January — 21 January
Delays possible Some carriageway incursion
Works location: A402
Works description: Excavate Trial Holes To Identify Cables For Future Works.
Responsibility for works: Esp Electricity Limited
Current status: Planned work about to start
A402 Goldhawk Road, London, Hammersmith And Fulham
20 January — 22 January
Delays possible Some carriageway incursion
Works location: A402
Works description: Build 1 Precast Chamber In 915mm X 445mm X 965mm Deep In Footway,Install 2m Of 1 Way Poly Duct In Footway
Responsibility for works: BT
Current status: Planned work about to start
A40 Westway, London, Hammersmith And Fulham
19 January — 19 January
Delays possible Some carriageway incursion
Works location: A40
Works description: Dislodged Granite Kerbs Pedestrian Signing & Guarding 08:30 - 16:30
Responsibility for works: Transport For London
Current status: Planned work about to start
A40 Westway, London, Hammersmith And Fulham
20 January — 21 January
Delays possible Some carriageway incursion
Works location: A40
Works description: Cracked, Uneven Paving Pedestrian Signing & Guarding 08:30 - 16:30
Responsibility for works: Transport For London
Current status: Planned work about to start
B412 St Mark'S Road, London, Kensington And Chelsea
19 January — 19 February
Delays possible Some carriageway incursion
Works location: B412
Works description: Paving Works - 408m2
Responsibility for works: Kensington and Chelsea Royal Borough Council
Current status: Planned work about to start
Hammersmith Grove, London, Hammersmith And Fulham
19 January — 30 January
Delays possible Some carriageway incursion
Works location: -
Works description: -
Responsibility for works: Global Crossing (UK) Telecommunications
Current status: Planned work about to start
Silchester Road, London, Kensington And Chelsea
19 January — 06 February
Delays possible Traffic control (two-way signals)
Works location: -
Works description: -
Responsibility for works: National Grid Gas Plc
Current status: Planned work about to start

 

 

 