Roadworks around Shepherd's Bush


Where to expect traffic delays in the days ahead

A315/B408 Glenthorne Road, London, Hammersmith And Fulham
30 March — 15 April
Delays likely Lane closure
Works location: A315/B408
Works description: Connections Projects:New Individual Supply::Excavate 10m Trench Across Road For 4 Way Duct Run, Excavation In South F/W For 2 Hv Joints, Excavation In North F/W For 1x Lv Joint, Pull 2 X 25 Of Triplex Cable From Joint Position To Tc, Pull 1 X 15m Of 300mmwv Cable From Joint Position To Tc
Responsibility for works: UK Power Networks
Current status: Advanced planning
 
A40 Westway, London, Hammersmith And Fulham
30 March — 31 March
Delays likely Lane closure
Works location: A40
Works description: Cpp Block Closure Wb# Testing Lights& Bollards, Bulk Clean & Change, Sweeping, Gully & Beany Block Cleaning, Barrier Works, Grass Cutting, Sign Cleaning, Debris Patrols Nearside Lane Closures With Offside Lane Running - All Vehicle Movements Maintained 23:00 - 05:00
Responsibility for works: Transport For London
Current status: Planned work about to start
A40 Westway, London, Kensington And Chelsea
30 March — 31 March
Delays likely Lane closure
Works location: A40
Works description: Cpp Block Closure Wb# Testing Lights& Bollards, Bulk Clean & Change, Sweeping, Gully & Beany Block Cleaning, Barrier Works, Grass Cutting, Sign Cleaning, Debris Patrols Nearside Lane Closures With Offside Lane Running - All Vehicle Movements Maintained 23:00 - 05:00
Responsibility for works: Transport For London
Current status: Planned work about to start
A219 Shepherd'S Bush Road, London, Hammersmith And Fulham
31 March — 02 April
Delays possible Some carriageway incursion
Works location: A219
Works description: Install 11m Of 1 Way Poly Duct In Footway
Responsibility for works: BT
Current status: Planned work about to start
A315/B408 Glenthorne Road, London, Hammersmith And Fulham
30 March — 09 April
Delays possible Some carriageway incursion
Works location: A315/B408
Works description: Network Operations Maintenance:Install / Replace Link Box: (Approx Depth 450mm):Lb No. 120413 - A - Replace A Very Poor Condition Link Box In The Footway. Until The Excavation On A Link Box Is Complete We Are Unaware On Totally What We May Find. If Service Cables Are Found That Could Be To Blocks Of Flats, Businesses Or Houses Then We Need To, By Law Give All Customers 5 Days Notice That Their Electric Supply Will Be Interrupted For Up To 8 Hours.
Responsibility for works: UK Power Networks
Current status: Planned work about to start
A402 Holland Park Avenue, London, Kensington And Chelsea
31 March — 08 April
Delays possible Some carriageway incursion
Works location: A402
Works description: New Customer Connection - Lay A New Gas Service Approx, 5m In Footway
Responsibility for works: Fulcrum Pipelines Limited
Current status: Planned work about to start

 