Roadworks around Shepherd's Bush


Where to expect traffic delays in the days ahead

Roadworks

A219 Wood Lane, London, Hammersmith And Fulham
02 February — 13 February
Delays likely Lane closure
Works location: A219
Works description: Retaining Wall Works Lane 1 Closure And Localized Pedestrian Management On Footway. 1.2m Clearance To Be Kept At All Times. 22:00 - 05:30
Responsibility for works: Transport For London
Current status: Planned work about to start
A219 Wood Lane, London, Hammersmith And Fulham
03 February — 04 February
Delays likely Lane closure
Works location: A219
Works description: Thames Water Sewer Works, No Excavation, Chamber Opening Only. Works To Take Place On 03/02/15 Between 2200-0500 (04/02/15)
Responsibility for works: Thames Water
Current status: Planned work about to start
A219 Wood Lane, London, Hammersmith And Fulham
03 February — 04 February
Delays likely Lane closure
Works location: A219
Works description: Thames Water Sewer Worlks, No Excavation, Manhole Opening Only. Works To Take Place On 03/02/15 Between 2000-0500 (04/02/15)
Responsibility for works: Thames Water
Current status: Planned work about to start
A40/A3220 West Cross Route, London, Kensington And Chelsea
03 February — 05 February
Delays likely Road closure
Works location: A40/A3220
Works description: Cpp Cyclical Routine Maintenance Full Closure & Diversions Sb Closure 0302 Nb Closure 0402 2300 To 0500
Responsibility for works: Transport For London
Current status: Planned work about to start
A402 Goldhawk Road, London, Hammersmith And Fulham
02 February — 04 February
Delays likely Traffic control (priority working)
Works location: A402
Works description: Install 2m Of 1 Way Poly Duct In Footway
Responsibility for works: BT
Current status: Planned work about to start
A40 Westway, London, Hammersmith And Fulham
02 February — 15 February
Delays likely Road closure
Works location: A40
Works description: Retaining Wall Works Full Closure 22:00 - 05:30 Tman Ref N1400443-001-W001
Responsibility for works: Transport For London
Current status: Planned work about to start
St Ann'S Road, London, Kensington And Chelsea
02 February — 04 February
Delays likely Traffic control (two-way signals)
Works location: -
Works description: -
Responsibility for works: Department For Transport Stats Roads
Current status: Planned work about to start
West Cross Route (A3220), London, Hammersmith And Fulham
03 February — 05 February
Delays likely Road closure
Works location: -
Works description: -
Responsibility for works: Transport For London
Current status: Planned work about to start
A219 Wood Lane, London, Hammersmith And Fulham
02 February — 04 February
Delays possible Some carriageway incursion
Works location: A219
Works description: Excavate 5m3 To A Depth Of More Than 1200mm To Allow For Duct Repositioning In Footway,Reinstate 5m2 Following Excavation In Footway,Reinstate 5m3 Following Excavation In Footway
Responsibility for works: BT
Current status: Planned work about to start
A3220 Addison Road, London, Kensington And Chelsea
03 February — 17 February
Delays possible Some carriageway incursion
Works location: A3220
Works description: Construct A New Manhole In The Front Light Well Of 100 To Install An Anti-Flooding Device To Prevent Internal Sewer Flooding To The Property. Materials Compound Required In The Carriageway O/S 100
Responsibility for works: Thames Water
Current status: Planned work about to start
A3220 Holland Road, London, Kensington And Chelsea
03 February — 05 February
Delays possible Some carriageway incursion
Works location: A3220
Works description: Service Pipe Repair In C/Way And Fway In Footway. Our Intention Is Tocomplete The Permanent Reinstatement In The Same Phase
Responsibility for works: Thames Water
Current status: Planned work about to start
A3220 Holland Road, London, Kensington And Chelsea
03 February — 05 February
Delays possible Some carriageway incursion
Works location: A3220
Works description: Service Pipe Repair In Cway / Fway In Carriageway. Our Intention Is Tocomplete The Permanent Reinstatement In The Same Phase
Responsibility for works: Thames Water
Current status: Planned work about to start
A4020 Uxbridge Road, London, Hammersmith And Fulham
02 February — 21 April
Delays possible Some carriageway incursion
Works location: A4020
Works description: Imga160404. Replace 203m 26" Ci With 203m Of 500mm Pe 0 Servicesaffected.
Responsibility for works: National Grid Gas Plc
Current status: Advanced planning
A4020 Uxbridge Road, London, Hammersmith And Fulham
03 February — 04 February
Delays possible Some carriageway incursion
Works location: A4020
Works description: Customer Connection New Residential Supply. Clear Blocked Tee & Repair Blockages If Found, Footway Works Only
Responsibility for works: Virgin Media
Current status: Planned work about to start
Hopgood Street, London, Hammersmith And Fulham
03 February — 05 February
Delays possible Some carriageway incursion
Works location: -
Works description: -
Responsibility for works: Hammersmith and Fulham London Borough Council
Current status: Planned work about to start

 

 

 

February 2, 2015