Track will be shut for signalling upgrade for four days in August
Engineers working on signalling upgrade. Picture: Network Rail
South Western Railway services will be further disrupted this summer by planned engineering works between Hounslow and Barnes.
In a bid to improve reliability by upgrading signalling, Network Rail engineers will be working on the line between Saturday 13 to Tuesday 16 August, meaning buses will replace trains on that line for four days, including two working days. This will affect stations including Chiswick, Brentford, Kew Bridge, Isleworth and Syon Lane.
The closure coincides with the game between Brentford and Manchester United at the Brentford Community Stadium on Saturday 13 August so fans will have to make alternative plans for getting to and from the match.
The work in August, on the railway known as the Hounslow Loop, will see bases for new signals – the traffic lights of the railway – installed along with new cabling.
The programme, which will finish in 2024, is replacing fault-prone 1970s signalling infrastructure that controls the safe movement of trains, with a modern equivalent that will be much more reliable.
Once all those renewals and upgrades are complete, Network Rail will move control of the signalling system from Feltham and Wokingham to the Wessex Rail Operating Centre (ROC) in Basingstoke.
The project reached the halfway stage over the May bank holiday when new signalling kit was switched on in the Ascot and Virginia Water area, with new signalling technology on the Hounslow Loop set to go live in August next year 2023, before the final phase in Wokingham is switched on in 2024.
Network Rail’s managing director for Wessex route, Mark Killick, said, “This is part of a massive £375m scheme to improve the railway in the area. Resignalling schemes like this one, and the track work that goes with it, are one of the best ways we have of improving the reliability of our network, so it’s really important we do the job and I’m grateful to our customers for their patience.
“By doing this work over four days, rather that splitting it up between weekends, means we can get much more done and we can make more progress on improving the railway with less disruption to our customers.”
Christian Neill, customer experience director for South Western Railway, commented, “The modernisation work that Network Rail is carrying out will significantly boost the reliability and performance of the railway for many years to come.
“The decision to close the railway for four days, including two working days on the Monday and Tuesday, has not been taken lightly. We urge all customers intending to travel from Saturday morning until the end of Tuesday to check before they travel and make use of the alternative transport options available.
“We’d like to thank those customers impacted by these works for their patience and understanding as this vital upgrade is carried out.”
Like Reading Articles Like This? Help Us Produce More This site remains committed to providing local community news and public interest journalism. Articles such as the one above are integral to what we do. We aim to feature as much as possible on local societies, charities based in the area, fundraising efforts by residents, community-based initiatives and even helping people find missing pets. We've always done that and won't be changing, in fact we'd like to do more. However, the readership that these stories generates is often below that needed to cover the cost of producing them. Our financial resources are limited and the local media environment is intensely competitive so there is a constraint on what we can do. We are therefore asking our readers to consider offering financial support to these efforts. Any money given will help support community and public interest news and the expansion of our coverage in this area. A suggested monthly payment is £8 but we would be grateful for any amount for instance if you think this site offers the equivalent value of a subscription to a daily printed newspaper you may wish to consider £20 per month. If neither of these amounts is suitable for you then contact info@neighbournet.com and we can set up an alternative. All payments are made through a secure web site. One-off donations are also appreciated. Choose The Amount You Wish To Contribute. If you do support us in this way we'd be interested to hear what kind of articles you would like to see more of on the site – send your suggestions to the editor. For businesses we offer the chance to be a corporate sponsor of community content on the site. For £30 plus VAT per month you will be the designated sponsor of at least one article a month with your logo appearing if supplied. If there is a specific community group or initiative you'd like to support we can make sure your sponsorship is featured on related content for a one off payment of £50 plus VAT. All payments are made through a secure web site. |