Lane Closures on North Circular Near Chiswick Roundabout to Resume
Work on improving Gunnersbury Avenue safety to last through to Summer

A4020 Broadway, West Ealing

03 April — 09 April

Delays likely Lane closure

Works description: New Water Supply HH Plots 1-6, 6x25mm MDPE mtrd 6P Supply works infoo tway and in Carriageway. Our intention is to complete the PermanentReinstatement in the same phase

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU307000808200620135-001

A4020,B455 The Broadway, Ealing

07 April — 10 April

Delays likely  Lane closure

Works description:  SEWER CLEANING EMERGENCY

Responsibility for works:  THAMES WATER

Current status:  Planned work about to start

Works reference:  MU026002141HNBZ--000001

A4020 Broadway, West Ealing

08 April — 12 April

Delays likely  Lane closure

Works description:  IMGC190310 Lane out on Busy Junc. required to lay a 32mm Servicetofrontof building with external steel riser to meter position inside 1st floor. Connection to existing main in carriageway near side.

Responsibility for works:  Cadent

Current status:  Planned work about to start

Works reference:  AZ0071000807791

A4020 Broadway, West Ealing

03 April — 09 April

Delays likely Lane closure

Works location: Unknown

Works description: New Water Supply HH Plots 1-6, 6x25mm MDPE mtrd 6P Supply works infoo tway and in Carriageway. Our intention is to complete the Permanent Reinstatement in the same phase

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU307000808200620135-001

B455 Haven Green, Ealing

05 April — 09 April

Delays likely Lane closure

Works location: Unknown

Works description: REMEDIAL WORKS TO CARRY OUT HA DEFECT

Responsibility for works: Scottish and Southern Power Distribution

Current status: Planned work about to start

Works reference: LP551S30001535

B4491 Popes Lane, Ealing

18 March — 24 May

Delays likely Traffic control (multi-way signals)

Works description: EXCAVATE TRENCH INSTALL CABLE CARRY OUT JOINTING BACKFILL AND REINSTATE

Responsibility for works: Scottish and Southern Power Distribution

Current status: Planned work about to start

Works reference: LP705S30001052

A4000, A40 Western Avenue, Acton

27 February — 23 September

Delays likely Road closure

Works description: Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required

Responsibility for works: Transport for London

Current status: Advanced planning

Works reference: YG432342348

Westway,  Hammersmith and Fulham

27 February — 23 September

Delays likely Road closure

Works description: Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required

Responsibility for works: Transport for London

Current status: Advanced planning

Works reference: YG432342350