Forthcoming Roadworks in the Ealing Area
Closures and diversions which may cause problems
Lane Closures on North Circular Near Chiswick Roundabout to Resume
Work on improving Gunnersbury Avenue safety to last through to Summer
A4020 Broadway, West Ealing |
03 April — 09 April |
Delays likely Lane closure |
Works description: New Water Supply HH Plots 1-6, 6x25mm MDPE mtrd 6P Supply works infoo tway and in Carriageway. Our intention is to complete the PermanentReinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU307000808200620135-001 |
|
A4020,B455 The Broadway, Ealing |
07 April — 10 April |
Delays likely Lane closure |
Works description: SEWER CLEANING EMERGENCY |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU026002141HNBZ--000001 |
A4020 Broadway, West Ealing |
08 April — 12 April |
Delays likely Lane closure |
Works description: IMGC190310 Lane out on Busy Junc. required to lay a 32mm Servicetofrontof building with external steel riser to meter position inside 1st floor. Connection to existing main in carriageway near side. |
Responsibility for works: Cadent |
Current status: Planned work about to start |
Works reference: AZ0071000807791 |
|
A4020 Broadway, West Ealing |
03 April — 09 April |
Delays likely Lane closure |
Works location: Unknown |
Works description: New Water Supply HH Plots 1-6, 6x25mm MDPE mtrd 6P Supply works infoo tway and in Carriageway. Our intention is to complete the Permanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU307000808200620135-001 |
|
B455 Haven Green, Ealing |
05 April — 09 April |
Delays likely Lane closure |
Works location: Unknown |
Works description: REMEDIAL WORKS TO CARRY OUT HA DEFECT |
Responsibility for works: Scottish and Southern Power Distribution |
Current status: Planned work about to start |
Works reference: LP551S30001535 |
|
B4491 Popes Lane, Ealing |
18 March — 24 May |
Delays likely Traffic control (multi-way signals) |
Works description: EXCAVATE TRENCH INSTALL CABLE CARRY OUT JOINTING BACKFILL AND REINSTATE |
Responsibility for works: Scottish and Southern Power Distribution |
Current status: Planned work about to start |
Works reference: LP705S30001052 |
|
A4000, A40 Western Avenue, Acton |
27 February — 23 September |
Delays likely Road closure |
Works description: Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required |
Responsibility for works: Transport for London |
Current status: Advanced planning |
Works reference: YG432342348 |
|
Westway, Hammersmith and Fulham |
27 February — 23 September |
Delays likely Road closure |
Works description: Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required |
Responsibility for works: Transport for London |
Current status: Advanced planning |
Works reference: YG432342350 |
|
April 8, 2019
|