Forthcoming significant roadworks in the W4 area
The following roadworks are likely to cause some delays in the Chiswick area
Lane Closures on North Circular Near Chiswick Roundabout to Resume
Work on improving Gunnersbury Avenue safety to last through to Summer
12 February — 12 February |
||
Delays likely Road closure |
||
Works location: Level crossing |
||
Works description: Dig wet bed |
||
Responsibility for works: Network Rail |
||
Current status: Advanced planning |
||
Works reference: KL156HOU-08-75-120219 |
13 February — 14 February |
||
Delays likely Traffic control (multi-way signals) |
||
Works description: Access existing BT Network to provide new fibre cable for new customer connection |
||
Responsibility for works: Openreach |
||
Current status: Planned work about to start |
||
Works reference: BC005CC8W0000000WAKH588P |
21 January — 15 February |
||
Delays likely Traffic control (two-way signals) |
||
Works description: IMGA192368 MAINS CONNECTIONS FOR ASSOCIATED WORKS IN KINGSBRIDGE AVENUE |
||
Responsibility for works: Cadent |
||
Current status: Advanced planning |
||
Works reference: AZ0071000763594 |
21 January — 19 March |
||
Delays likely Contra-flow |
||
Works description: Phase 1a - 1f Utility works, drainage and re-profiling works. |
||
Responsibility for works: Transport for London |
||
Current status: Planned work about to start |
||
Works reference: YG432343386 |
|
||||||||||
|
||||||||||
|
14 December — 13 February |
||
Delays likely Traffic control (Stop/Go boards) |
||
Works description: Temporary Structure Licence - Crane |
||
Responsibility for works: Ealing |
||
Current status: Planned work about to start |
||
Works reference: DV008TS0387 |
24 November — 22 February |
||
Delays likely Lane closure |
||
Works description: Phase 1a - 4 Utility works, drainage and re-profiling works. |
||
Responsibility for works: Transport for London |
||
Current status: Advanced planning |
||
Works reference: YG432334046 |
Source: www.roadworks.org
February 12, 2019