Traffic Delays Likely in Chiswick
Forthcoming significant roadworks in the W4 area
The following roadworks are likely to cause some delays in the Chiswick area.
A205 Chiswick High Road (North Circular Road), Chiswick |
20 August — 04 September |
Delays likely Lane closure |
Works location: A205 |
Works description: Excavate Of 30" Water Main To Remove A Defect Section Of Approx 150m Under Railway Embankment, Working For Optimise On Behalf Of Thames Water |
Responsibility for works: Thames Water |
Current status: Planned work about to start |
|
A315 Chiswick High Road, Chiswick |
20 August — 04 September |
Delays likely Lane closure |
Works location: A315 |
Works description: Excavate Of 30" Water Main To Remove A Defect Section Of Approx 150m Under Railway Embankment, Working For Optimise On Behalf Of Thames Water |
Responsibility for works: Thames Water |
Current status: Planned work about to start |
|
A315 High Street, Brentford |
22 August — 05 September |
Delays likely Road closure |
Works location: A315 |
Works description: Sewer Failure--Works Intended To Include First Time Permanent Reinstatement Within Same Phase |
Responsibility for works: Thames Water |
Current status: Work in progress |
A3000 Heathfield Terrace, Chiswick |
24 August — 26 August |
|
|
Delays likely Road closure |
|
Works location: A3000 |
|
|
Works description: Pfi Carriageway Micro Surfacing |
|
|
Responsibility for works: Hounslow London Borough Council |
|
|
Current status: Planned work about to start |
|
|
Cornwall Grove, Chiswick |
23 August — 30 August |
Delays likely Road closure |
Works location: - |
Works description: - |
Responsibility for works: Hounslow London Borough Council |
Current status: Planned work about to start |
|
Lonsdale Road, Chiswick |
22 August — 29 August |
Delays likely Road closure |
Works location: - |
Works description: - |
Responsibility for works: Hounslow London Borough Council |
Current status: Planned work about to start |
|
Park Drive, Acton |
22 August — 29 August |
Delays likely Road closure |
Works location: - |
Works description: - |
Responsibility for works: Hounslow London Borough Council |
Current status: Planned work about to start |
|
Quick Road, Chiswick |
23 August — 30 August |
Delays likely Road closure |
Works location: - |
Works description: - |
Responsibility for works: Hounslow London Borough Council |
Current status: Planned work about to start |
|
Duke Road, Chiswick |
24 August — 31 August |
|
|
Delays likely Road closure |
|
Works location: - |
|
|
Works description: - |
|
|
Responsibility for works: Hounslow London Borough Council |
|
|
Current status: Planned work about to start |
|
|
|
|
Fraser Street, Chiswick |
24 August — 31 August |
|
|
Delays likely Road closure |
|
Works location: - |
|
|
Works description: - |
|
|
Responsibility for works: Hounslow London Borough Council |
|
|
Current status: Planned work about to start |
|
|
|
|
Grosvenor Road, Chiswick |
25 August — 01 September |
|
|
Delays likely Road closure |
|
Works location: - |
|
|
Works description: - |
|
|
Responsibility for works: Hounslow London Borough Council |
|
|
Current status: Planned work about to start |
|
|
|
|
Harvard Hill, Chiswick |
25 August — 01 September |
|
|
Delays likely Road closure |
|
Works location: - |
|
|
Works description: - |
|
|
Responsibility for works: Hounslow London Borough Council |
|
|
Current status: Planned work about to start |
|
|
|
|
Milnthorpe Road, Chiswick |
25 August — 02 September |
|
|
Delays likely Road closure |
|
Works location: - |
|
|
Works description: - |
|
|
Responsibility for works: Hounslow London Borough Council |
|
|
Current status: Planned work about to start |
|
|
|
A4 Great West Road, Brentford |
17 August — 29 September |
Delays likely Road closure |
Works location: A4 |
Works description: Carriageway Resurfacing |
Responsibility for works: Transport For London |
Current status: Advanced planning |
|
A307/A205 Kew Road, Kew |
01 August — 25 September |
Delays likely Road closure |
Works location: A307/A205 |
Works description: Installation Of Temporary Barriers, Refurbishment And Replacement Of Service Bay Cover Slabs |
Responsibility for works: Transport For London |
Current status: Advanced planning |
|
Source: www.roadworks.org
August 26, 2016
|