Planned roadworks in the W4 area
The following roadworks are likely to cause some delays in the Chiswick area:
|
|||||||
|
04 September — 08 September Traffic control (two-way signals) |
||
Delays likely due to Streetworks |
||
Responsibility: Thames Water |
||
EToN status: Planned work about to start |
02 September — 11 September Road closure |
||
Delays likely due to Streetworks |
||
Responsibility: Hounslow London Borough Council |
||
EToN status: Advanced planning |
|
|
05 May — 09 September |
||
Delays likely Lane closure |
||
Works location: A406 |
||
Works description: Install 140m Of 24 Poly Ducts In Carriageway |
||
Responsibility for works: BT |
||
Current status: Advanced planning |
07 March — 30 November |
||
Delays likely Lane closure |
||
Works location: A4/A3005 |
||
Works description: Strengthening Works At Piers 19,20& 30 And 38-103 On The A4 Great West Rd With Night Time Lane Closures Between Chiswick ( Larch Drive & Boston Manor Rd During The Hours Of 10.30pm To 05.00am Mondays-Sundays Inclusive. Lane Closures Will Be A Lane 1 & 2 Closure With Lane 3 Running Or A Lane 2 & 3 Closure With Lane 1 Running Both East And West Bound On The A4 . See Package 3 Works Location Drawing Attached : Drawing 5103542/Dr/St/Wp3/001 Coordinated With Hammersmith Flyover |
||
Responsibility for works: Highways Agency |
||
Current status: Planned work about to start |